Posted on: June 1, 2023
Contractors have discovered a lack of existing asphalt on the road and will use additional material to complete the project. A change order was signed by the Board of County Commissioners and funds were allocated to produce a quality product.
Road and Bridge Department
Posted on: May 24, 2023
The repaving of Piedra Road (CR 600) has been postponed by the contractor to begin removing asphalt Tuesday June 6th. The project is expected to be complete by end of August. Expect delays and detours during this process.
Road and Bridge Department
Posted on: April 26, 2023
In November of 2022, CDOT gave the County 90 days to remedy structural and safety conditions of the bridge based off a routine report by Stantec completed in October 2022. The County Public Works and Transportation departments, as well as, County Administ...
Read on...
Road and Bridge Department